- Sprint Name: Dim Sum
- Scrum Master: KZ
- Dashboards
- Product Backlog
- Scrum Wall [developers view]
- Deployed environments
- master [developers only]
- staging [testers only]
- production
- Releases ChangeLogs
Issue | Title | Presenter | Status | Duration | Start Time |
---|---|---|---|---|---|
#68 | Everyone at z43 uses osparc | PC MaG | In progress | 10min | 16:00 |
#21 | UI for data-processing modules S-D7, Y3M2,4,5,2-12 | SAN | In progress | 3min | 16:10 |
#16 | o2S2PARC API, S-D12, Y3M5 | PC | In progress | 2 min | 16:13 |
#505 #12 |
Large Models/Results Rendering & Interaction (M9; D4.a) Postpro workbench; S-D15, Y3M6 |
IP MaG | In progress | 10min | 16:15 |
#130 | TI Solutions Treatment Planning, N-D2 | MaG | In progress | 2min | 16:25 |
#22 | Fine Grained Access Rights S-D6,Y3M6 | OM | In progress | 3min | 16:27 |
#38 | IT’IS tissue property database S-D5 | OM | Done | 5min | 16:30 |
#162 #163 #164 |
UI/UX: dashboard cleanup, study sheet cleanup, light theme | OM | In progress | 10min | 16:35 |
#1426 | Platform Stability: testing, monitoring, diagnostics and maintenance S-D21 | SAN PC | In progress | 5min | 16:45 |
Deliverable | Due | Title | % Done | Notes |
---|---|---|---|---|
J-D3 | M1 | Retreat prep | 100 | Retreat has taken place |
J-D15 | M1 | Documentation agreement | 75 | Requirements established |
S-D26 | M1 | Idea Lab subaward | 100 | The subaward has been setup and preparations are ongoing |
S-D2 | M2 | OpenCOR / CellML module & PMR S-D2, M2 #1069 | 75 | First version implemented, will be revisited as part of the simplified creation of data analysis services task |
J-D33 | M2 | Publication linking, J-D33, Y3M2,8 #33 | 100 | Meta-data sections throughout SIM-CORE support linking to pdf, webpages; awaiting MAP-CORE functionality to automatically surface publications (based on DOI?) |
J-D3 | M2 | Retreat | 100 | |
J-D6.a | M2 | Conference list | 50 | |
J-D21 | M2 | DRC feedback/issue collection and tracking (Infrastructure) - J-D21 #1065 | 100 | |
J-D28.a | M2 | Portal testing (Testing and Infrastructure) - J-D28 #1066 | 100 | oSPARC end-to-end testing infrastructure established |
J-D7.a | M2 | simple creation of data-processing modules, S-D7, Y3M2,4,5,2-12 #21 | 100 | survey drafted, work on functionality started |
S-D24 | M2 | UI/UX subaward | 100 | first phase contracted, ongoing |
S-D7a | data analysis and visualization | 25 | survey has been drafted | |
S-D3g | metrics | 75 | metrics have been selected and prepared for presentation to steering committee | |
S-D18 | M3 | NEUROFAUNA rat | 75 | |
J-D3e | M3 | DRC Governance strategies | 100 | |
J-D4 | M3 | slide-decks (marketing material) | 80 | Worked on it this sprint- should be completed soon |
J-D16 | ongoing | Workshops and webinars | 50 | one workshop completed, ongoing |
J-D20 | M3 | White paper outlining SPARC data standards and QC metrics for SPARC data depositors | ||
J-D29 | M3 | Data access/cost structure | ||
S-D10 | M4 | macro/templates, towards guided mode | 100 | |
S-D22 | M5 | AWS | 100 | |
S-D12 | M5 | o2S2PARC API | ||
S-D7 b, c | M5 | simple creation of osparc services | ||
S-D20 | M5 | NEUROCOUPLE Keast team collaboration | ||
S-D6 | M6 | Fine-grained access rights | UI Improvements | |
S-D15 | M6 | Advanced Postpro | ||
S-D5 | M7 | IT’IS tissue property database | ||
S-D21 | M1-12 | DevOps/Platform stability | ||
N-D1 | -- | everyone at Z43 uses osparc | ||
N-D2 | -- | TI planning tool |
- S-D18: decaying rat prevents reimaging required to properly segment the PNS; registration-based approach will be tried, to merge PNS images from previously scanned rat
- Continuous work on Platform stability is time-consuming but essential work and may delay other milestones